For a 6-month, $1,000,000 construction contract, problems rarely appear “all at once.” They show up first as small variances and behavioral signals that turn into schedule slips and cost overruns.
1. Schedule-Related Early Warning Signs (Weeks 2–6)
🔴 Missed Short-Interval Milestones
- Weekly look-ahead schedules not being met
- Tasks consistently rolling forward OR NOT SCHEDULED
- Inspections or approvals not requested on time
Why it matters:
If early milestones slip, the project rarely catches up without added labor overtime or sub costs.
🔴 Excessive Float (Deposit money) Consumption
- Critical path activities using float earlier than planned
- Schedule updates show a negative float, possibly indicating delays
Early signal:
The schedule still shows an on-time completion, but contingency time is already gone.
2.Cost & Financial Red Flags (Often First 30–60 Days)
🔴 Labor Hours Exceed Budget Early
- Actual labor hours forecast greater than planned hours for completed work
- Overtime introduced earlier than expected
- Crew productivity below estimate, aka early overtime
Rule of thumb:
If 25–30% of the schedule is complete but 40%+ of labor is consumed, you have a problem.
🔴 Cost-to-Complete Trending Up
- Forecasted cost at completion is creeping upward with each update
- Project manager reluctant to update projections
Key metric:
Early negative earned value variance (EV < 1.0) is a strong predictor of final loss.
3.Scope & Change Management Issues
🔴 High Volume of RFIs (request for information) Early
- RFIs spike in the first 30–45 days
- Design clarifications increasing instead of decreasing
Why this is dangerous:
Unresolved RFIs stall crews, cause rework, and lead to unpriced changes.
🔴 Change Orders Not Priced or Approved Promptly
- Field work proceeding pending CO approval
- Verbal directives without written authorization
- Change log growing faster than revenue recognition
Early margin erosion indicator:
Work is happening faster than billing approvals.
4.Procurement & Materials Red Flags
🔴 Long-Lead Items Not Released Immediately
- Submittals are late or rejected multiple times
- Materials ordered without final approval
- Vendor lead times longer than estimated
Common outcome:
Acceleration costs later: air freight, overtime, resequencing.
🔴 Subcontractor Performance Drift
- Subs requesting early payments
- Subs missing manpower commitments
- Increased back-charges or disputes
5.Cash Flow & Billing Warning Signs
🔴 Billings Lag Work Performed
- Underbilling due to unresolved changes
- Retention grows faster than expected
- Owner payment delays tied to documentation issues
Why this matters early:
Cash strain caused by poor decisions involving rushed work.
6.Management & Behavioral Signals Often Overlooked
🔴 “Optimism Bias” in Reporting
- Status reports remain “green” despite missed milestones
- Unresolved issues described as minor repeatedly
- PM resists external review or detailed questioning
🔴 Increased Firefighting
- Daily plans are changing constantly
- PM and superintendent reactive, not proactive
- Less time spent planning, more time fixing problems
7.Simple Early-Warning Dashboard (Best Practice)
| Indicator | Healthy | Warning |
|---|---|---|
| Schedule % complete vs time elapsed | ≥ equal | Behind |
| Labor hours used vs % complete | ≤ equal | >10% over |
| Cost variance (EV) | ≥ 1.0 | < 0.95 |
| Open RFIs | Declining | Increasing |
| Unapproved change value | <2% | >5% |
| Cash collected vs earned | ≥90% | <80% |